Adani Power LimitedPower & UtilitiesADANIPOWER
Q2 FY27 concall · earnings callAdani Power Limited
Adani Power delivered record Q2 FY27 results on 11.5% volume growth, higher PLF and realization, boosted by one-time Gujarat PPA revenue, while advancing its 24 GW thermal pipeline and hydro entry.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Power sales volume Q2 FY27 | 26.4 billion units | +11.5% YoY | |
| Total continuing revenue Q2 FY27 | ₹17,528 Cr | +28.5% higher YoY basis | |
| Continuing EBITDA Q2 FY27 | ₹6,321 Cr | more than 18% YoY | |
| Reported EBITDA Q2 FY27 | ₹8,743 Cr | +45.7% YoY | |
| Consolidated PAT Q2 FY27 | ₹7,019 Cr | +141.5% YoY |
From filed quarterly results. YoY and QoQ compare each metric on the same accounting basis.
| Quarter | Revenue | Net profit (PAT) | Basic EPS |
|---|---|---|---|
| Q3 FY25 | ₹13,671.18 Cr+5.2% YoY+2.5% QoQ | ₹2,940.07 Cr+7.4% YoY-10.8% QoQ | ₹7.67+16% YoY-6.6% QoQ |
| Q2 FY25 | ₹13,338.88 Cr+2.7% YoY-10.8% QoQ | ₹3,297.52 Cr-50% YoY-15.7% QoQ | ₹8.21-50.2% YoY-15.5% QoQ |
| Q1 FY25 | ₹14,955.63 Cr+35.9% YoY+11.9% QoQ | ₹3,912.79 Cr-55.3% YoY+42.9% QoQ | ₹9.72-55.6% YoY+46.6% QoQ |
| Q4 FY24 | ₹13,363.69 Cr+30.5% YoY+2.9% QoQ | ₹2,737.24 Cr-47.8% YoY0% QoQ | ₹6.63-48.2% YoY+0.3% QoQ |
| Q3 FY24 | ₹12,991.44 Cr+67.3% YoY0% QoQ | ₹2,737.96 Cr+31119.6% YoY-58.5% QoQ | ₹6.61Turned positive YoY-59.9% QoQ |
- Power sales grew 11.5% to 26.4 billion units with PLF at 70.1% versus 62.8% last year on strong demand and weak monsoon.
- Total continuing revenue rose 28.5% to INR17,528 crores and continuing EBITDA to INR6,321 crores; reported PAT rose 141.5% to INR7,019 crores including INR2,422 crores prior-period Gujarat PPA revenue.
- Fuel cost rose 41.8% to INR10,229 crores on volumes and higher imported coal cost; finance cost fell 9.7% to INR760 crores and credit rating was upgraded from AA to AA+.
- Secured 25-year 1,320 megawatts PPA from Uttarakhand, entered hydro via 330-megawatt Alaknanda CIRP resolution and 770-megawatt Bhutan JV, and synchronized first 660 MW Korba Phase-II unit.
“India needs abundant and reliable baseload power supply using domestic coal.”
| Topic | What management said |
|---|---|
| Fuel cost and tariff pass-through | Management said higher fuel cost was driven by volumes and approximate 50% rise in landed imported coal cost; Gujarat PPA indexation lags by more than 6 months so Q2 fuel rise will reflect after two quarters, while Bangladesh PPA passes through immediately. |
| Haryana DISCOM revenue derecognition | Management said 50% of Haryana DISCOM alternate coal compensation claim received was reversed on auditor advice as conservative accounting pending final settlement; cash is retained and no net interest outgo is foreseen. |
| EBITDA growth drivers | Management said EBITDA growth versus FY26 reflects full utilization of acquired capacities, new medium-term PPAs at good tariffs, tariff indexation to import coal indices, and 35% to 40% domestic coal use at Tuticorin lowering fuel cost. |
| Future PPA bids | Management said UP bids are submitted, West Bengal 1,600 MW and Rajasthan bids due early next month, with Rajasthan state-specific and West Bengal location-specific while UP and Gujarat allow anywhere in India; no tie-up done with AESL. |
- Korba Phase-II first 660 MW unit has achieved grid synchronization with commercial commissioning expected shortly in Q3; second unit planned for quarter 4 of '27.
- 1,600 MW Mahan Phase-II targeted for commercial operations in early Financial Year '28.
- Secured long-term PPAs for 62% of upcoming 24 gigawatt thermal pipeline, including 1,320 megawatts from Uttarakhand Power Corporation Limited for Korba 2.
- Normal PLF expectation for thermal portfolio is around 65% versus 70.1% in Q2 FY27 and 74.1% in H1 FY27.
- Peak debt expected around INR1 lakh crores by FY30 or FY31 versus INR61,860 crores total debt at September 30, 2026.
Summary written from the transcript filed by Adani Power Limited for the call held on 26 Oct 2026; published 1 Nov 2026, 18:15 IST.