Cemindia Projects LimitedInfrastructure & ConstructionCEMPRO
Q2 FY27 concall · earnings callCemindia Projects Limited
Cemindia reported 25% YoY Q2 revenue growth with stable execution, raised INR1,400 crores via QIP, secured ratings upgrades, and reached an all-time high order book of INR32,715 crores while maintaining 20-25% growth and 10% plus margin guidance.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Total operating income - Q2 FY27 | ₹2,749 Cr | up by 25% YoY from ₹2,195 Cr in Q2 FY26 | |
| EBITDA - Q2 FY27 | ₹280 Cr | up 15% Y-o-Y from ₹243 Cr in Q2 FY26 | |
| EBITDA margin - Q2 FY27 | 10.2% | compared with 11.1% in Q2 FY26 | |
| PAT - Q2 FY27 | ₹131 Cr | up 21% YoY from ₹108 Cr in Q2 FY26 | |
| Total operating income - H1 FY27 | ₹5,470 Cr | up 15% YoY from ₹4,772 Cr in H1 FY26 | |
| EBITDA - H1 FY27 | ₹565 Cr | up 12% YoY from ₹504 Cr in H1 FY26 | |
| PAT - H1 FY27 | ₹271 Cr | up 10.8% YOY from ₹245 Cr in H1 FY26 | |
| Order book | ₹32,715 Cr | all-time high |
From filed quarterly results. YoY and QoQ compare each metric on the same accounting basis.
| Quarter | Revenue | Net profit (PAT) | Basic EPS |
|---|---|---|---|
| Q3 FY25 | ₹2,244.86 Cr+11.3% YoY+12.8% QoQ | ₹87.04 Cr+10.7% YoY+20.6% QoQ | ₹5.07+11.2% YoY+21% QoQ |
| Q2 FY25 | ₹1,990.87 Cr+23.6% YoY-16.4% QoQ | ₹72.20 Cr+34.5% YoY-27.9% QoQ | ₹4.19+34.3% YoY-28.1% QoQ |
| Q1 FY25 | ₹2,381.49 Cr+30% YoY+5.5% QoQ | ₹100.18 Cr+91.4% YoY+11.9% QoQ | ₹5.83+91.8% YoY+11.9% QoQ |
| Q4 FY24 | ₹2,257.72 Cr+38.4% YoY+11.9% QoQ | ₹89.56 Cr+137.8% YoY+13.9% QoQ | ₹5.21+136.8% YoY+14.3% QoQ |
| Q3 FY24 | ₹2,017.16 Cr+52% YoY+25.3% QoQ | ₹78.60 Cr+113.1% YoY+46.4% QoQ | ₹4.56+114.1% YoY+46.2% QoQ |
- Q2 FY27 operating income INR2,749 crores up 25% YoY, EBITDA INR280 crores up 15% YoY at 10.2% margin, PAT INR131 crores up 21% YoY.
- H1 FY27 operating income INR5,470 crores up 15% YoY, EBITDA INR565 crores at 10.3% margin, PAT INR271 crores.
- Raised INR1,400 crores via QIP at INR1,108 per share and received upgrades with ICRA AA (Stable), CARE AA- (Stable) and CRISIL AA (Stable).
- Order inflow INR3,487 crores in Q2 and INR2,481 crores in October, taking order book to INR32,715 crores with data center around 15%.
- Vadhavan Port work has restarted, Bangladesh job substantially completed and paid, and bid pipeline is around INR1.3 lakh crores external plus group opportunities.
“Our target of INR25,000 crores for this year will definitely be achieved, and it can cross also.”
| Topic | What management said |
|---|---|
| Margins and H2 outlook | Management said new jobs including Vadhavan Port, Morsagar, Munger, K-RIDE, DMRC and Pune have not yet crossed threshold for margin recognition and will convert after one or two quarters; maintained around 10% average margin for the year. |
| Order inflow detail | Q2 inflow of around INR3,400 crores was mostly marine and data center including Andhra Pradesh data center around INR1,000 crores, Dhamra Port around INR800 crores, Project Varsha INR700 crores and JSW INR235 crores; October INR2,481 crores included Jaipur Metro INR781 crores, K-RIDE INR660 crores and Assam Dhubri INR1,000+ crores. |
| Revenue, capex and L1 | Management maintained 20%-25% revenue growth, guided H2 capex of INR150 crores-INR200 crores with large TBM capex up to INR1,500 crores likely in FY28, and said no tender is currently in L1 position. |
| Data centers | Six data centers under execution with civil work advanced and electromechanical vendors finalized for first two; large revenue from electromechanical erection expected from January and in Q4; data center margins not expected to exceed 10% as it is not specialized work. |
| Group vs external pipeline | Group share is roughly 53%-54% of order book and around 70% plus of recent influx, with H1 revenue around 35%-36% from group; external bid pipeline is around INR1.3 lakh crores plus additional internal group opportunities, with group capex addressable market estimated around INR50,000 crores. |
| Vadhavan Port | Work at Vadhavan Port has started after one and a half years but management declined to guide on revenue pace; port order book of INR7,500 crores includes INR1,500 crores for Vadhavan. |
- Maintain revenue growth guidance of 20%-25% for the year
- Maintain EBITDA margin of around 10% plus on average through the year
- Target INR25,000 crores order inflow for this year, expected to be achieved and possibly exceeded
- H2 capex of around INR150 crores-INR200 crores; large diameter TBM capex of up to INR1,500 crores likely to be deployed in FY28 with 14-16 months deployment timeline
- Look forward to 25% CAGR on top line for next three years
Summary written from the transcript filed by Cemindia Projects Limited for the call held on 6 Nov 2026; published 15 Nov 2026, 19:42 IST.