Q2 FY27 concall · earnings callIndian Metals & Ferro Alloys Limited

Q2 and H1 FY27 were higher year on year on added KNR-2 capacity and better prices, with KNR-1 commissioning underway to lift Q3 output past 100,000 tons despite slight price moderation and higher met coke costs.

Positive tone4-minute briefPublished 11 days after the call

Numbers
MetricThis quarterChangeFive-quarter trend
FY27 ferrochrome production guidance380,000 tons—
Q2 average realisation₹0.01 Cr—
Q2 EBITDA per tonabout INR28,000—
Q1 EBITDA marginclose to 30%—
Financials

From filed quarterly results. YoY and QoQ compare each metric on the same accounting basis.

QuarterRevenueNet profit (PAT)Basic EPS
Q3 FY25₹643.22 Cr-6.1% YoY-7% QoQ₹93.37 Cr-14.3% YoY-25.4% QoQ₹17.30-14.1% YoY-25.3% QoQ
Q2 FY25₹691.92 Cr-0.1% YoY+4.5% QoQ₹125.21 Cr+40.1% YoY+10.5% QoQ₹23.17+40.2% YoY+10.6% QoQ
Q1 FY25₹662.28 Cr-5.6% YoY-5.5% QoQ₹113.34 Cr+2.6% YoY+78.3% QoQ₹20.95+2.4% YoY+31% QoQ
Q4 FY24₹700.56 Cr+10% YoY+2.2% QoQ₹63.57 Cr-0.9% YoY-41.7% QoQ₹15.99+34.7% YoY-20.6% QoQ
Q3 FY24₹685.27 Cr+9.9% YoY-1.1% QoQ₹108.95 Cr+886.9% YoY+21.9% QoQ₹20.15+902.5% YoY+21.9% QoQ
TL;DR
  • Q2 and H1 FY27 performance was noticeably higher than last year on new capacity and better prices
  • KNR-2 reached about 84,000 tons per annum in October, expected at about 100,000 tons per annum by December after transformer change
  • KNR-1 first furnace tapped hot metal on August 25th, second furnace expected around 15th of November, with Q3 quarterly output expected to cross 100,000 tons
  • Board approved capex of about INR375 crores to raise Mahagiri underground from 6 lakh tons to 7.5 lakh tons and to produce low-carbon ferrochrome
  • Prices moderated slightly from Q1 to Q2 with slight further moderation expected, while met coke costs moved up to around 375 to 380 marks
Said on the call

“So we remain confident about the industry and we remain especially confident by God's grace about IMFA's own position, where we have worked very hard to build resilience and competitiveness into the business model.”

Subhrakant Panda
From the Q&A
TopicWhat management said
South Africa ramp and global balanceManagement said South African output collapsed in 2025 and is reviving on special tariffs, and expects higher South African ferrochrome to be offset by lower output elsewhere, primarily China, keeping chrome units broadly balanced with possible interim turbulence.
Ore raising seasonalityManagement said Q2 ore raising was seasonally lower due to extended monsoon affecting opencast output, and maintained FY27 target of 1 million tons with longer-term target beyond 1.2 million tons.
Costs and met cokeManagement attributed higher cost per ton to higher met coke around 375 to 380 marks, higher underground ore mix and royalty, plus startup and power-grid threshold inefficiencies at Kalinganagar, expected to normalize after December 2026 with renewable flow from late November.
Sales mix and China exportsManagement said exports were 90-10 at 160,000 tons output and target about 60-40 by 2028, about 300,000 tons exports and 200,000 tons domestic from half a million tons, with China currently about 120 odd thousand tons per annum rising toward 180 to 200,000 tons.
Ethanol projectManagement guided ethanol revenue of INR320 crores at around 10% EBITDA, 45-60 days working capital and internal IRR of 15%, with returns dependent on grain prices.
Guidance
  • Maintain FY27 ferrochrome production guidance of 380,000 tons and FY28 volume guidance of around 475,000 tons
  • Expect Q3 quarterly output to cross 100,000 tons for the first time, with Q4 higher to meet full-year target
  • Expect second KNR-1 furnace hot metal tapping around 15th of November and KNR-2 to reach full rated capacity of about 100,000 tons per annum by December
  • Expect partially built furnace at KNR-2 to be operational around July 2027, subject to permissions
  • Target 1 million tons of ore raising in FY27 and progress Mahagiri expansion from 6 lakh tons to 7.5 lakh tons toward beyond 1.2 million tons
Source
Same sector

Others in Metals & Mining

All Metals & Mining →
  • Electrosteel Castings LimitedQ2 FY27Cautious tone

    Q2 FY27 saw flat DI pipe volumes at 1.21 lakh tons and subdued 8.9% EBITDA margins amid slow JJM execution, with management expecting only a marginal H2 improvement before a stronger recovery in FY28 supported by valves and paints diversification.

    DI pipes, fitting and CI pipes sales volume (Q2)
    1.21 lakh tonsvs 1.20 lakh tons in Q1 FY27
    Consolidated total income (Q2)
    ₹1,558 Cr+6.4% QoQ
    ELECTCASTMetals & MiningVerified brief5 guidance items
  • Nupur Recyclers LimitedQ2 FY27Positive tone

    Nupur Recyclers delivered its strongest quarter in Q2 FY27 on higher scrap volumes and a shift to value-added manufacturing, while advancing extrusion expansions and a Q4 FY27 LFP battery recycling plant.

    Q2 FY27 Total revenue
    ₹116.21 Cr+124.86% YoY vs ₹51.68 Cr in Q2 FY26
    Q2 FY27 EBITDA
    ₹15.73 Cr+148.48% YoY vs ₹6.33 Cr in Q2 FY26
    NRLMetals & MiningVerified brief5 guidance items
  • Q2 FY27 revenue grew 25% Y-o-Y to INR1,632 crores but margins compressed to 12% EBITDA and 5.2% PAT on market iron ore and higher coal costs, with recovery dependent on Q3 mining clearances and beneficiation ramp-up from Q4.

    Consolidated revenue Q2 FY27
    ₹1,632 Cr+25% Y-o-Y
    Consolidated revenue H1 FY27
    ₹3,382 Cr+29% Y-o-Y
    GPILMetals & MiningVerified brief7 guidance items
  • H1 FY27 revenue grew 33% year-on-year to INR1,639 crores on a scale-up in copper, while lead volumes and margins were pressured by West Asia-linked supply-chain disruptions.

    H1 FY27 revenue
    ₹1,639 Cr+33% YoY
    H1 FY27 PAT
    ₹55.6 Cr
    POCLMetals & MiningVerified brief5 guidance items
  • Scoda Tubes LimitedQ2 FY27Positive tone

    Q2 FY27 revenue was largely flat year-on-year at INR148.9 crores with margins compressed by power, fuel and freight costs and seamless competition, while management retained 20% to 25% FY27 revenue growth guidance on H2 recovery and Q4 FY27 welded commissioning.

    Revenue from operations Q2 FY27
    ₹148.9 Cr+2.5% YoY vs ₹145.3 Cr in Q2 FY26
    Revenue from operations H1 FY27
    ₹273.3 Cr+12.6% YoY vs ₹242.7 Cr in H1 FY26
    SCODATUBESMetals & MiningVerified brief6 guidance items