Prabha Energy LimitedEnergyPRABHA
Q2 FY27 concall · earnings callPrabha Energy Limited
Prabha Energy's maiden call framed H1 FY27 as infrastructure-stage with small cascade sales and net profit above full-year FY26, with material revenue expected from FY28 after grid connectivity.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Portfolio area | approximately 398 square kilometers | — | |
| Estimated in-place hydrocarbon reserves | over 32.45 billion cubic meters | — | |
| Current cascade sales | around 20,000 cubic meters per day | — | |
| Expected combined peak production | more than 1.5 MMSCMD | — | |
| Capex for balance 47 Jharia wells | somewhere above ₹500 Cr | — |
- Upstream CBM and marginal-field portfolio of five fields in three assets across approximately 398 square kilometers.
- H1 FY27 net profit exceeded full-year FY26 but operating revenue remains modest on cascade sales of around 20,000 cubic meters per day.
- Near-term triggers are Jharia pipeline by January 2027 and North Karanpura pipeline by March 2027 to enable grid sales.
- Combined peak of more than 1.5 MMSCMD targeted by FY28-29 from 68 completed North Karanpura wells and 55 total Jharia wells.
“We are sure you all would be able to comprehend the exponential growth which awaits our company from FY’28 onwards.”
| Topic | What management said |
|---|---|
| Starting volumes | Initial Jharia commercial volumes of 20,000 to 40,000 cubic meters a day from 8 wells, ramping with 47 more wells; North Karanpura to start at a few lakh cubic meters per day after pipeline connects. |
| Peak timeline | Peak in 1.5 to 2 years, in FY28-29, at around 9 lakh from North Karanpura and around 7 lakh from Jharia for more than 1.5 MMSCMD combined versus 20,000 cubic meters per day today, with 25-year block life. |
| Economics and pricing | Jharia carries 90% revenue-sharing versus 25% participating interest in North Karanpura, making Jharia more revenue-accretive; blocks are open-price and can be sold to anyone including via IGX once grid-connected. |
| Accounting and returns | Expenditure is capitalized as test production; capitalization will stop once production and sales ramp up post-pipeline, with North Karanpura capex largely done and payback seen in less than four years at full quantity. |
- Jharia block 8-km pipeline to Urja Ganga expected by January 2027 with initial production from Q4 FY'27
- North Karanpura 68-km evacuation pipeline by IOCL expected by March 2027 with higher sales from next financial year
- Drill additional 47 wells in Jharia block starting next financial year at capex of somewhere above INR500 crores, targeted around 50% from equity and 50% from debt or internal accruals
- Expect optimal-capacity EBITDA of 70% to 75% on estimated operating cost of around 20% only
Summary written from the transcript filed by Prabha Energy Limited for the call held on 5 Nov 2026; published 15 Nov 2026, 20:34 IST.