Q2 FY27 concall · earnings callBehari Lal Engineering Limited
Q2 FY27 grew revenue about 22% and PAT about 28% year-on-year on volume and richer high-value mix, while sequential margin slipped on lagged pass-through of firmer scrap and power costs.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Revenue from operations Q2 | ₹154.2 Cr | up 21.7% versus same quarter last year | |
| EBITDA including other income Q2 | ₹27.6 Cr | up 26.9% YoY | |
| Profit-after-tax Q2 | ₹17.4 Cr | up 27.7% YoY | |
| High-value products share of revenue Q2 | 62.9% | versus 57.8% for full-year '25-'26 and 60.4% in Q1 | |
| Order book at end of September | ₹179.4 Cr | — |
Versus Q1 FY27, high-value mix rose to 62.9% from 60.4%, Q2 EBITDA margin of 17.9% was below Q1's 19.6% on input-cost firming and price lag, and the balance sheet reflects the listing with net-worth at INR427.3 crores and INR62.6 crores of issue proceeds still unutilized while Unit 3 remains under construction for start-up next year.
- Revenue from operations was INR154.2 crores against INR126.6 crores in the same quarter last year, a growth of 21.7%; H1 revenue was INR305.8 crores against INR255.1 crores, a growth of 19.9%.
- EBITDA including other income was INR27.6 crores at 17.9% margin against 17.2% last year; H1 EBITDA was INR57.4 crores at 18.8% against 18%.
- Profit-after-tax was INR17.4 crores, up 27.7%, at net margin of 11.3%; H1 profit after tax was INR36.6 crores, up 26%.
- High-value products were 62.9% of Q2 revenue against 57.8% for the full-year '25-'26 and 60.4% in Q1, which held margins as input costs firmed.
- Order book was INR179.4 crores for three to four months execution; net-worth was INR427.3 crores with term-loan paid-off and INR114.6 crores in cash and bank balances.
“That shift is deliberate and is the single biggest lever we have on profitability.”
| Topic | What management said |
|---|---|
| IPO proceeds | Of the INR93 crores fresh issue, INR30.4 crores utilized as at 30th September 2026 with INR62.6 crores unutilized, mostly in bank deposits. |
| Unit-3 commissioning | Unit-3 ICDP and HSS rolls expected next year; management says huge inquiries, first trial lots after start with repeat orders in one or two months, with margin benefit from import substitution. |
| Sequential profit dip | Year-on-year profit up about 26% to 27% but sequentially lower on scrap, alloy and power cost firming with 2-3 month selling-price lag; realizations could improve next quarter. |
| Order book and mix | Order book of INR179.4 crores is about three to four months execution, split similar to sales with 55% to 60% metal rolls and castings and 5% to 10% exports, 90% of exports from engineering castings. |
| Customer concentration | Top-10 customers contribute less than 50% and no customer more than 10%; more than 1,900 customers served with more than 1,500 in metal rolls. |
- Unit-3 construction ongoing with commissioning expected next year, including ICDP and HSS import-substitute rolls, with trial lots to follow start of production
- No quantitative guidance for the second-half; management said realizations could improve next quarter but gave no definite number
- Defense and aerospace expected to contribute considerably from next year after in-house NABL accredited laboratory and participation through GEM portal
- Rooftop solar planned till the end of the current financial year and grounded solar in the first-half of next financial year, with savings expected by the end of next financial year