Q2 FY27 concall · earnings callVikram Solar Limited
Q2 FY27 volumes fell to 591 MW on deferred IPP and C&I offtake, but order intake doubled to 1.7 GW and EBITDA per watt rose 37% on richer distribution and DCR mix ahead of cell integration.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Revenue from operations (Q2) | ₹1,077 Cr | lower than Q1 | |
| Sales volume (Q2) | 591 MW | lower than Q1 | |
| EBITDA per watt peak | INR1.71 per watt | up 37% sequentially from INR1.25 per watt peak | |
| EBITDA (Q2) | ₹101 Cr | down from ₹126 Cr in Q1 | |
| Revenue (H1 2027) | ₹2,641 Cr | up 18% YoY | |
| Closing order book | 8.2 GW | — |
- Volume at 591 MW and revenue at INR1,077 crores were lower than Q1 on IPP evacuation/land deferrals, monsoon and delayed C&I decisions.
- Order flow at 1.7 GW was more than double the previous quarter; closing order book stands at 8.2 GW after removing 1 GW of unviable U.S. export orders.
- EBITDA per watt rose 37% sequentially from INR1.25 per watt peak to INR1.71 per watt as distribution rose to 259 MW and DCR volumes grew.
- 9 GW TOPCon Plus cell facility expects first cell out in December with project COD in March 2027 to support DCR supply and margins.
“To close my comments, I will say that Q2 volumes were lower, but we enter H2 with better unit economics, a broader customer base, and a strong order book.”
| Topic | What management said |
|---|---|
| Order book mix and cell margin benefit | Management said the 8.2 GW order book is primarily non-DCR and 60%-70% should execute over the next 12-18 months; captive cells should almost double present DCR margins based on procured cells, but declined to quantify. |
| Capex and BESS timeline | Management said 9 GW cell capex is about INR4,500 crores, wafer-ingot 9 GW about INR5,600 crores and 7.5 GWh BESS about INR3,600 crores; Phase 1 BESS assembly faces no export-control delay with first container and certifications next quarter. |
| Volume decline and H2 recovery | Management attributed Q2 volume fall to IPP offtake deferrals on evacuation and land constraints plus monsoon and delayed C&I decisions after July 18 ALMM List-II clarity, and said offtake is normalizing with around 1 GW in coming quarter a fair estimate. |
| Distribution vs DCR mix | Management said distribution caters both to PM Surya Ghar DCR and small C&I non-DCR; DCR volume grew 71% quarter-on-quarter while distribution was 44% of volume, supporting EBITDA per watt. |
- First cell out in December, with lines commissioned sequentially over the following three months and project COD in March 2027
- 60%-70% of the 8.2 GW order book to be executed over the next 12-18 months
- For H2, EBITDA per watt peak to hold at around current levels with volumes substantially higher than H1 as the order book converts
- In FY28, with the 9 GW TOPCon Plus cell facility commissioned, a significant share of volume to move to higher-margin DCR segment
Summary written from the transcript filed by Vikram Solar Limited for the call held on 16 Nov 2026; published 20 Nov 2026, 18:01 IST.