Q2 FY27 delivered robust revenue with sequential margin improvement as earlier price revisions flowed through, supported by a INR1,950 crores DG-set order book led by data centers, while fresh steel, copper and aluminum inflation continues to delay full margin recovery.
| Metric | This quarter | Change | Five-quarter trend |
|---|---|---|---|
| Q2 FY27 Consolidated Revenue | ₹847 Cr | — | |
| Q2 FY27 EBITDA | approximately ₹128 Cr | — | |
| Q2 FY27 PAT | approximately ₹71 Cr | — | |
| Q2 FY27 EBITDA Margin | 15.2% | — | |
| Q2 FY27 PAT Margin | 8.4% | — | |
| H1 FY27 Consolidated Revenue | ₹1,628 Cr | +12.5% YoY | |
| Q2 Genset Business Powered by Cummins Growth | 14% year-on-year increase | +14% YoY | |
| Cummins Power DG Set Order Book as of October 2026 | ₹1,950 Cr | — |
- Q2 FY27 revenue was INR847 crores with EBITDA margin of 15.2% and PAT margin of 8.4%; H1 revenue was INR1,628 crores with EBITDA margin of 14.4% and PAT margin of 8.3%.
- Sequential margin improvement was driven by price revisions, but profitability remains impacted by elevated commodity prices and lag in passing costs to customers.
- Cummins Power DG-set order book was INR1,950 crores as of October 2026 including approximately INR1,200 crore of data-center orders executable over 12-18 months.
- DG sets contributed 80.6% of H1 revenue with 6.5% EBITDA margin while wind power contributed 19.4% with 47.4% EBITDA margin; Cummins gensets grew 14% year-on-year in Q2.
- Wind roadmap targets 638 MW from around 330 MW operating plus 50 MW under construction and 250 MW of new GUVNL/SECI wins, with 70% debt funding and continued third-party EPC.
“demand is not constrained, but engine availability remains the key factor for influencing execution.”
| Topic | What management said |
|---|---|
| Price hikes and RM inflation | Management said current pricing covers input costs as they stand today with revisions done at detailed rating and product level, but pass-through is lagged because the INR1,950 crores order book is a mix of old and new pricing and data-center orders execute over 12-18 months while other orders execute in days to six months. |
| Data-center contribution and execution | Management said data centers were about 20% of H1 contribution and order book includes approximately INR1,200 crore of data-center orders with a robust inquiry pipeline, but H2 execution quantum depends on site readiness and acceptance. |
| Ex-data-center demand and competition | Management said ex-data-center demand is robust in manufacturing, real estate and rental with steady growth in low horsepower and strong MHP/HHP traction; low horsepower is price-sensitive with more players while high horsepower including QSK has limited competition and forms the core of the order book with no new entrants seen. |
| Wind power roadmap | Management disclosed operational capacity of around 330 MW with 50 MW under construction, plus 250 MW won in reverse auctions including 100 MW GUVNL, 50+ MW GUVNL and 100 MW SECI to reach about 630 MW toward the 638 MW target; tenders have 24 months to execute after PPA signing. |
| Steady-state margins | Management said steady-state genset margin on a consolidated basis is about 9%, wind IPP blended margin including old and new is between 60%-65% on average 62% with new projects at 82%-85%, and EPC at about 10%. |
- Continue to expect double-digit revenue growth through financial year 2027
- Planning further very calibrated price hikes during the current quarter while expecting some moderation in raw material cost once geopolitical conditions improve
- Wind capacity target of 638 MW to be achieved in next two and a half years, thereafter add 100-150 MW of renewable energy projects year-on-year towards 1 GW ambition
Summary written from the transcript filed by Powerica Limited for the call held on 16 Nov 2026; published 20 Nov 2026, 17:59 IST.